They missed the deadline. Then they wanted a meeting.
70-plus sites, almost 20 fines, just over the border
Email down on deadline day
|
|
|
Friday’s Microsoft outage didn’t catch us. But if we’d had submissions due, or an adjudicator waiting on a reply, we’d have been in a world of hurt. More on that in the Two-Minute Fix.
Straight in.
|
|
|
|
Doing the Rounds
QLD · QBCC · 9 November 2026
The tolerances guide is online. Check it’s the one you’re measured by.
|
|
Whose number is it?
| The QBCC Guide | Written mainly for houses, and their garages, sheds and pools (Class 1 and 10 buildings). |
| Your contract | Takes over wherever it asks for a higher standard than the Guide. |
| Apartments and commercial | Start with your spec, and the Standards it names. |
| On site | Ask where the number comes from, and how it’s measured. |
|
| FIND THE NUMBER BEFORE YOU FIX ANYTHING. |
|
| QBCC Standards and Tolerances Guide, December 2023 edition |
|
| • | On 9 November the QBCC put two new resources online: an Industry Learning Hub and a Licensee Essentials page. |
| • | The hub has an interactive version of the QBCC Standards and Tolerances Guide, financial compliance material for licensees and their accountants, and National Construction Code learning modules. |
| • | Licensee Essentials puts licence obligations, what each licence class covers, insurance, and contracts, deposits and payments on one page. |
| • | Handy. But the Guide says it was written mainly for houses. And where your contract asks for a higher standard, the contract wins. |
|
What it means for you
Earlier this month I walked an apartment job in south-east Queensland while the builder put a level on hobs and window rebates. The number was 3mm in 3m. I asked if that was the Australian Standard. No, it was the contract’s.
That’s the question to ask every time someone puts a level on your work. Which document is that number from?
If it’s your contract, read what it says, and how it says to measure. A tolerance with no method of measurement is an argument waiting to happen.
If it’s the Guide, check the Guide covers the job. On a house it usually will. On apartments or commercial, your spec comes first.
And next time you price a job, read the tolerances in the spec as hard as you read the rates.
The Guide is free on the QBCC Industry Learning Hub.
Queensland. General information, not advice on your job.
|
|
|
|
The Number
70+
Northern Rivers sites the NSW Building Commission visited in October. Almost 20 fines. Top of the list: residential building work without a NSW licence.
|
|
|
The blitz ran in mid-October across 16 localities, from Banora Point and Kingscliff down to Byron Bay and Yamba. More than 70 houses and apartment blocks. Almost 20 fines, worth more than $10,000 all up.
The most common offence was doing residential building work without the right NSW licence. Next was missing site signage.
Plenty of Gold Coast trades take work just over the border. The Commission’s point is that builders and subcontractors doing residential work must be licensed. In NSW.
So before you start a NSW job, check what licence NSW needs from you, and whose name it has to be in: yours, or your company’s. Then sign the contract. Working unlicensed can cost you more than a fine when it’s time to get paid.
Building Commission NSW, 5 November 2026.
|
|
|
|
Off My Desk
They missed the deadline. Then they wanted a meeting.
|
|
Where the argument goes
| Payment schedule | 15 business days to say what’s wrong with the claim, and why. In writing. |
| No schedule | The builder owes the amount claimed. In adjudication it doesn’t get to answer. |
| A meeting weeks later | Pressure. Not a defence. |
| Your clock | Still running. Keep the application on track. |
|
| THE TIME TO ARGUE IS THE SCHEDULE. |
|
|
|
A tiler in south-east Queensland served a payment claim on his builder in October.
The builder had 15 business days to answer it with a payment schedule. Nothing came.
A few days after the deadline, the builder sat him down. The claim was overclaimed, he was told, by fifteen to twenty grand. The variations needed trimming. The builder would measure up and pay something by Friday, then they’d settle. And his late start had cost the builder money, so that might come off too.
None of it in writing. A week later the builder’s accounts team emailed nine questions about the claim. Still no amount, and still no schedule.
Here’s the one line he needed:
|
|
The time to say I’ve overclaimed was the payment schedule.
|
|
|
In Queensland the builder gets one go at arguing your claim. It’s the payment schedule: 15 business days, in writing, with its reasons.
Miss it, and the builder owes the amount claimed. If it goes to adjudication, the builder doesn’t get to put in a response at all. The overclaim, the variations, the late start: none of it is in front of the adjudicator.
So a meeting weeks later isn’t a defence. It’s pressure. And it’s a common pattern: promise a payment, keep you talking, and let your time to adjudicate run out.
What we did. Kept the application on track, built to go in on time, whatever turns up in the meantime. If a deal comes along he’s happy with, he can choose not to lodge it, or withdraw it.
What we didn’t do. Argue the claim by email. He could answer plain questions of fact, and did. But every email arguing the numbers is a chance to muddy the water.
What it teaches. The time to tell you you’ve overclaimed is the payment schedule. After that, it’s talk.
Watch for. “We’ll pay something by Friday.” Take the money if it comes. Don’t stop the clock for it.
One more. Check your own figures against your bank statements before you lodge. If a payment’s been missed off your claim, you own it and take it off. You don’t send a new claim.
Queensland, under the BIF Act. Live matter, no outcome yet. General information only.
Details changed. The lesson isn’t.
|
|
|
|
Two-Minute Fix
Email down on deadline day? Sort plan B now.
Most adjudicators deal with you by email and nothing else. So does most of your paperwork. Friday was the warning.
| 1. | Don’t leave it to the last day. A response, submissions or a notice goes a day early. (Not a payment claim. That’s on or after your date, never before.) |
| 2. | Set up a second email account now, with a different provider, and keep the login handy. If your main one goes down, you can still send, and say why it’s coming from a different address. |
| 3. | Know the other way in. The builder’s registered office from an ASIC search, for a notice by hand or post. And the phone number for the registry or the nominating authority. |
| 4. | Keep the proof. Screenshot the outage page and the error, write down the times, and save any bounce. A bounce means it didn’t go. |
| 5. | Don’t count on an outage buying you time. The deadlines in the Act don’t move for one. |
And the Christmas cliff: Queensland’s was yesterday. Victoria’s is Monday 23 November, NSW is Thursday 26 November, on the longest terms. On or after your date. Never before.
|
|
|
|
|
The Toolbox
The notice delivery checklist, free
One page for whoever sends the notices. Email, hand delivery and post: what to check before you write “given” on the file.
One signed copy for every person the contract names. Every address in the To line. A bounce means it wasn’t given. And what to do when the email’s down.
|
|
|
|
Free PDF, no sign-up. Print it and stick it above the desk. It’s a starting point. Your contract’s notices clause decides who gets what, and how.
|
|
|
|
The Academy Bit · this is the ad
A subbie I’m working with was asked to agree liquidated damages at a daily rate. No programme. No finish date. His question did the work: “How can I agree to liquidated damages if I haven’t got a program?”
He’s right. Before you agree an amount of money, you need to know what that money’s at risk by. So the answer to the builder was: happy to talk a rate and a cap, once there’s a programme.
Contract Risk Review, $2,750 + GST.
Every clause and every schedule read before you sign. Liquidated damages and the cap, retention and when it comes back, the time bars, the tolerances, the lot.
You get a departures schedule you can hand straight to the builder, a walkthrough call so you know what you’re asking for and why, and one round of dealing with their response.
Or reply to this email, or ring me, and we’ll talk it through.
|
|
|
That's the week.
Has a builder ever wanted to argue your claim after the schedule deadline had gone? Hit reply and tell me what you did.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.