QLD · Supreme Court · 30 October 2026
Won the adjudication. Lost it in court. Because of a date.
|
|
How the date sank it
| Contract ended | 28 September 2025, when the parties signed the main contract for the job. |
| Last claim date | 28 September 2025. No more claim dates after that. |
| Adjudicator used | Monthly claim dates after the contract had ended. They didn’t exist. |
| The claim also had | Work done after 28 September. |
|
| A $100,050.50 DECISION. VOID. |
|
| Hauton Rd Childcare v Checkpoint Construction [2026] QSC 262 |
|
| • | On 30 October the Queensland Supreme Court threw out an adjudication decision worth $100,050.50. |
| • | The claim was under an early works contract. That contract ended when the parties signed the main contract for the job. |
| • | In Queensland, when a contract ends and doesn’t keep its claim dates alive, the day it ends is its last claim date. No more monthly dates after that. |
| • | The adjudicator decided the claim on monthly dates that came after the contract had ended. Those dates didn’t exist. The Court said that was fatal, even though a good date was sitting right there. |
| • | The claim also took in some work done after that last date. The Court said a claim like that isn’t a valid claim at all. Same line of cases as the Gardner fact sheet in last week’s issue. |
|
What it means for you
If your contract has been ended, or replaced by a new one, the old contract has one last claim date: the day it ended. Claim that contract’s work against that date, and nothing done after it.
Work you do after that belongs to the new arrangement and gets claimed under it. Two contracts, two sets of claims. Don’t mix them on one invoice.
Coming back to a job on a new deal after the builder’s gone? That’s this week’s Off My Desk.
And put the date on the claim. The Act doesn’t make you, but somebody has to work out the right date sooner or later. Better it’s you.
One judge’s decision. Another Supreme Court judge went a different way on part of this last year, and the Court of Appeal hasn’t settled it. Play it safe.
Queensland only, under the BIF Act. General information, not advice on your job.
|
|
|
|
The Number
$194
The liquidator’s cheque, on a debt of close to $100,000. About two tenths of a cent in the dollar.
|
|
|
He rang me about the liquidator’s letter. He’d read it as a back charge. It was his dividend, nearly three years after the builder went under.
That’s where an unpaid trade sits at the end of a liquidation. Behind the secured lenders, sharing what’s left with everyone else.
So the money that counts is the money you collect while the builder’s still trading. Claim on your date every month. Chase an overdue claim this week, not next quarter. Don’t let a backlog build.
And read the liquidator’s letter before you panic. Most of them are less scary than they look.
CC&D client matter, 2026. Details changed.
|
|
|
|
Off My Desk
The builder’s gone. Now the owner wants you back.
|
|
Before the crew goes back in
| Who’s paying | The owner confirms in writing, from someone who can bind it. |
| The old builder | The owner confirms the builder’s contract has ended and the site is theirs. |
| Deposit | In the bank before you mobilise. |
| Invoices | Staged with the work. Not one at the very end. |
|
| AN EMAIL PROMISE ISN’T SECURITY. |
|
|
|
A metalwork subbie in south-east Queensland was part way through a job when the builder stopped paying its subbies. Within days the site was locked.
Most of his job was already fabricated and sitting in his yard.
A few weeks later the owner came to him direct. Would he come back and finish it? He sent a quote, the owner signed it, and the owner’s director put this in an email:
|
|
I can guarantee that invoice will be paid.
|
|
|
It’s a nice line. It’s still only a line in an email.
He’d already been burned once on this site. As I put it to him: “I’ve been bitten once. Don’t you think I need to be a bit shy the second time round?”
So before the crew went back in, we went through four things.
Who he was dealing with. When he asked who could sign for the owner, the owner’s side got a bit touchy. He asked anyway, and got it from a director in writing.
The old builder. Until the owner confirms the builder’s contract has ended and the owner has the site, you could be installing the builder’s scope, for the builder’s client, in the middle of their fight.
The deposit. The quote had one. It goes in the bank before anyone loads a truck.
What “completed” means. Paid within 24 hours of completion sounds quick. But the last item couldn’t even be measured until the concrete was in, weeks after everything else was up. Read literally, nearly all the money waited until the very end. Stage invoices that follow the work fix that.
What it teaches. The second job on a site that’s already burned you is where subbies get burned twice. Get the money and the paperwork sorted before the goodwill runs out.
Watch for. “Paid on completion” on a job where completion depends on someone else’s trade. And the old builder’s invoice: deal with it in writing, so nobody can say you’re being paid twice for the same work.
General information only. Your own contract and your own facts decide it.
Details changed. The lesson isn’t.
|
|
|
|
Two-Minute Fix
The Christmas cliff is next Monday.
Last week’s Christmas email. If it hasn’t gone, this is the week.
| 1. | Know your day. On the longest terms the Acts allow, the last day to put in a November claim and still be paid before Christmas is Monday 16 November in Queensland, Monday 23 November in Victoria and Thursday 26 November in NSW. |
| 2. | Sent the email already? Chase the answer today. A yes has to change the claim date itself, in writing. |
| 3. | Got a no, or no answer? Don’t send the November claim early anyway. In Queensland and NSW an early claim is no claim. In Victoria it’s saved, but it gains you nothing. |
| 4. | Put your December claim date in the diary now. If it falls in the shutdown, send it that day or any day after. |
On or after your date. Never before. Same rule in December.
|
|
|
|
|
The Toolbox
The key dates sheet, free
For anyone who missed it in Issue 07. One sheet per contract, ready to print: claim day, the builder’s answer, delay notice, EOT claim, the variation steps, completion, the defects period, retention and the final claim.
Fill in your claim day and your payment term, and the Christmas maths takes two minutes.
|
|
|
|
Free PDF, no sign-up. Print it and fill it in by hand. It’s a starting point. The dates come from your contract, not from the sheet.
|
|
|
|
The Academy Bit · this is the ad
Sunday, 3:56pm. Something on site means a 24 hour delay notice. Your contract says an email sent after 5pm is taken to be given at 9am the next business day.
That line tells you when your notice counts. It doesn’t move when it’s due. Due is 3:56pm Monday. Send it at 4:30pm Monday, thinking anything before 5pm counts as Monday, and you’re 34 minutes late.
That’s the kind of trap the Tradies Academy toolkit is built for.
It reads your own contract, finds the notice clauses and their deadlines, and drafts the Notice of Delay from that same contract. It never sends anything. You check it and press Send. And the first notice on each job comes to me for a free check.
Foundation places are still going: the toolkit and the whole Academy for $127 a week, locked in for as long as you stay. After that, the toolkit sits in its own tier at $197 a week.
It runs inside Claude on your own computer, so you’ll need your own paid Claude plan (Pro or above). I set it up with you.
Foundation places are hand-picked, so we’ll have a chat first. Not ready? Fair enough. Smoko’s still free every Tuesday.
|
|
|
That's the week.
Had an owner ask you back after the builder went? Hit reply and tell me how you handled it.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.