Morning.
Here's what's on this week:
|
One day that costs three weeks
Fourteen days that don’t count
“Our payment run is on Fridays.”
|
|
|
First up.
|
|
|
|
Doing the Rounds
QLD · VIC · NSW · The Christmas shutdown
Your November claim pays for Christmas. One day can push it into January.
|
Claim goes in Mon 16 Nov Paid by Mon 21 Dec |
Claim goes in Tue 17 Nov Paid by Mon 11 Jan |
|
| ONE DAY APART. THREE WEEKS APART. |
|
| Queensland, on the longest payment term the Act allows. |
|
| • | In Queensland and Victoria, 22 December to 10 January aren’t business days under the payment Acts. The builder’s clock to answer and pay your claim stops. In NSW it stops from 27 to 31 December. |
| • | So there’s a cliff. On the longest term the Act allows, a Queensland claim that goes in on Monday 16 November is paid by 21 December. One that goes in on Tuesday 17 November is paid by 11 January. |
| • | Victoria’s cliff falls between Monday 23 and Tuesday 24 November. NSW falls between Thursday 26 and Friday 27 November, and the later claim is paid by 4 January. |
| • | A claim on 30 November, on the longest terms: NSW is paid by 5 January, Victoria by 15 January, Queensland by 22 January. |
| • | These are the latest a builder can lawfully pay. If your contract pays sooner, you’re paid sooner. |
|
What it means for you
Here's the catch. Most of you can't claim on 16 November.
If your claim date is the 25th or the end of the month, a claim on the 16th for November work goes in early. In Queensland and NSW an early claim is no claim at all. In Victoria it's saved, but the builder's clock still starts on your claim date, so you gain nothing.
If you claimed in October, October's date is used. November's work can't go in until November's date. A day early is the same as a month early.
The only way over the cliff is to move the claim date itself, in writing, before you claim. Don't bank on a contract line saying an early claim “is taken to be made” on the claim date. Courts have thrown out early claims with that wording in the contract.
That's this week's Fix. It's worth doing this month. In December it's too late.
And if your December claim date falls in the shutdown, Christmas Day included? Send it that day or any day after. In Queensland and Victoria the builder's clock starts on 11 January either way. Just don't send it before the date.
Business days and payment terms under each state's payment Act, 2026-27. Your contract sets your claim date and your terms.
|
|
|
|
The Number
14
weekdays this Christmas that don’t count in Queensland and Victoria. NSW loses 4.
|
|
|
That's close to three working weeks where the builder's clock to answer your claim, and to pay it, stands still.
It's written into the Acts. The builder isn't being difficult, so there's nothing to argue about. There's only planning around it.
Victoria has one more twist. Work done between 22 and 31 December can't be claimed until 31 January. On the longest term, that's paid by 26 February.
Weekdays from 22 December 2026 to 10 January 2027. QLD and VIC exclude the whole period from business days; NSW excludes 27 to 31 December.
|
|
|
|
Off My Desk
Eight weeks without a progress payment. All of it legal.
|
|
How his Christmas ran
| Claim 25 Oct | Paid Friday 28 November. |
| Claim 25 Nov | Due Tuesday 20 January. Paid Friday 23 January. |
| Claim 25 Dec | Christmas Day. Held to the date. Due Monday 16 February. |
|
| NO PROGRESS PAYMENT FOR EIGHT WEEKS. |
|
|
|
Last Christmas a formwork subbie in south-east Queensland got the full treatment.
Claim date the 25th of every month. A payment term of 25 business days, which is as long as a Queensland subcontract can go. And a builder who applied the contract and the Act to the day.
His November claim fell due on Tuesday 20 January. The money landed on Friday the 23rd. The reason he was given:
|
|
Our payment run is on Fridays.
|
|
|
Three days late. And the builder knew three days was too short for anyone to do anything about it.
In Queensland you can suspend work for non-payment, but only after a written notice, and at least two business days after that. With the weekend and Australia Day on the Monday, the first working day he could have stopped was Tuesday 27 January. The money had landed four days before that. An adjudication takes weeks.
So the remedies are built for a builder who's weeks late. A builder who pays three days late every time gets away with it.
One thing went right. His December claim date was Christmas Day. The easy move was to send it before knocking off for the break. We made sure it didn't go. Sent early, it would have been no claim at all. Held to the date, it cost him nothing, because the builder's clock didn't start until 11 January anyway.
What it teaches. Your Christmas gets decided the day you sign the contract. The claim date, the payment term and the business day definition set the dates. The Act only sets the outer limit.
Watch for. “Paid on our next payment run”, or anything that ties your payment to the builder's own cycle. In Queensland a subcontract can't push payment past 25 business days. A payment run doesn't move the due date.
General information only. Your own contract sets your dates, so read your clause.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Send the Christmas email this week.
One email to the builder, before your November claim goes in.
| 1. | Find your claim date and payment term in the contract. Work out when your November claim actually gets paid. |
| 2. | If that's January, email the builder now. Ask if they'll bring the November claim date forward so it's paid before Christmas. |
| 3. | If they say yes, get the claim date itself changed in writing, for this claim. An email saying they'll accept it early won't do it. |
| 4. | Ask one more question while you're there: will they be paying over the shutdown? |
If they say no, at least you know now, while there's still time to plan for it.
|
|
|
|
|
The Toolbox
The Gardner fact sheet, free
Six pages on the Queensland case that makes a claim sent too early worth nothing. What happened, what the Court decided, how the other states compare, and a quick example with the 25th as the claim date.
Worth a read before anyone in your office is tempted to send the December claim before the break.
|
|
|
|
Free PDF, no sign-up. General information. Your contract sets your claim date.
|
|
|
|
The Academy Bit · this is the ad
That formwork subbie’s Christmas was set the day his contract was signed.
Contract Risk Review, $2,750 + GST.
Every clause and every schedule read before you sign. The claim date, the payment term, the business days, the time bars, retention, the lot.
You get a departures schedule you can hand straight to the builder, a walkthrough call so you know what you’re asking for and why, and one round of dealing with their response.
Got a new contract landing before the break? Send it over before you sign it.
Or reply to this email, or ring me, and we’ll talk it through.
|
|
|
That'll do.
Had a builder tell you the clock stops at Christmas? Hit reply and tell me how it went.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.
This is the web copy of Smoko, the weekly email from Construction Claims and Disputes. Get it in your inbox. General information only, not legal advice. PO Box 918, Paddington QLD 4064
|