 | BY CONSTRUCTION CLAIMS & DISPUTES | | NEWS, INSIGHTS & THE STUFF THAT MATTERS | Issue 07 · Tuesday 27 October 2026
|
|
Right then.
Here's what's on this week:
|
The regulator puts it in writing
One in eight invoices, two months late
“You told us. Not everything.”
|
|
|
Here we go.
|
|
|
|
Doing the Rounds
QLD · QBCC guidance · 20 October
|
Before you sign READ the delay and variation clauses |
Before you start WRITE the change down, with the price and the time |
|
|
|
| • | Last Tuesday the QBCC published guidance for its licensees on fixed-price contracts while costs keep moving. |
| • | Before signing, it says to weigh up how long the job runs, material lead times, and what the contract says about delays and variations. |
| • | On variations: pick up the impact early, and document the change before the work starts, with the price and the timing understood. |
| • | Its list of warning signs includes ongoing delays, growing variation disputes, shrinking margins and subcontractor payment pressure. |
| • | It's guidance, not a change to the law. |
|
What it means for you
“Just get on with it, we'll sort the paperwork later.” That line starts more variation fights than anything else I see.
Now there's a page from the regulator saying the opposite. It's written for licensees and their own contracts, but it reads straight across to yours.
It won't change what your contract says. Your contract still decides what you have to send, and by when. But next time a site manager waves away a price before the crew starts, you've got something to point to.
And read that list of warning signs from the other side. If a builder is slow paying you and fighting every variation, that's two of them.
Queensland guidance. Your own contract sets the steps.
|
|
|
|
The Number
13%
of construction invoices more than 60 days overdue in September. A year ago, 6%.
|
|
|
That's about one invoice in eight, and more than double where it was twelve months ago.
Across every industry it's one in ten. And fewer than half of all invoices, 48%, were paid by the due date.
A builder who's two months behind is running part of the job on your money. In most states, the payment Act puts a deadline on the builder's answer to a proper payment claim. Chase it on that clock, not on the builder's.
CreditorWatch, Business Risk Index, September 2026, as reported 14 October 2026.
|
|
|
|
Off My Desk
You told us. You didn’t tell us everything.
|
|
Something like this
| Claim day | The 25th. |
| Delay | Tell them within five days. |
| Variation | Price in before the crew starts. |
| Completion | Notice when we finish, and the date the defects period ends. |
|
| ONE SHEET. EVERY CONTRACT. |
|
|
|
A firm I work with hit a change on a government job. They did what almost every variation clause asks for. They told the client it was going to be a variation.
This clause asked for one more thing. A quotation, before the work carried on.
No price went in. And that was enough for the client to knock the claim back. As it was put to me, the client's answer came down to this:
|
|
…you might have told us, but you didn’t tell us everything.
|
|
|
To their credit, they owned it. The step was in the contract and it got missed.
Here's why it's so easy to miss. Variation clauses often have more than one step, and the steps have their own deadlines. A common shape is notice before you start the changed work, or within a few days of the direction, whichever comes first.
The “before you start” part is the one that bites. The crew starts the day they're told. By the time anyone in the office opens the clause, that deadline has already gone.
Some clauses want written notice. Some want a price. Some want the direction in writing first. Every contract is different, and nobody reads every clause every time something changes on site.
So on the call we landed on a fix. A sheet for every contract that comes back, with the handful of things you have to do every time. In my words on the call: “The twenty-fifth is the day. If there's a delay, you've got to tell them within five days. You've got to give them a quote before you start it.”
Pin it up in the office. Give a copy to whoever runs the job on site.
What it teaches. Telling them it's a variation is half the job. The clause decides the rest, and it usually decides it before the work starts.
Watch for. “Before commencing”, “prior to proceeding” and “whichever is the earlier” in your variation clause. That's where the deadline is hiding.
General information only. Your own contract sets the steps, so read your clause.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Put your busiest job on one sheet.
Start with the contract you're most likely to get a variation on this week.
| 1. | Find the payment clause. Write down the day your claims go in. |
| 2. | Find the delay clause. Write down how many days you have to give notice, and whether they're business days or calendar days. |
| 3. | Find the variation clause. Write down every step it wants before you start the changed work. Notice, price, written direction. |
| 4. | Put the clause number next to each line, and stick it where the person doing the paperwork will see it. |
If you can't tell what a clause wants, that's the one worth a proper look.
|
|
|
|
|
The Toolbox
The key dates sheet, free
The sheet from this week's Fix, ready to fill in. Claim day, the builder's answer, delay notice, EOT claim, the variation steps, dockets, completion notices, the defects period, retention and the final claim.
Each line has a hint for where to look in the contract, and columns for the clause, the time, when the clock starts, what the notice has to say, and what missing it costs.
|
|
|
|
Prefer to print it? Get the PDF
Free, Word or PDF, no sign-up. It’s a starting point. The dates come from your contract, not from the sheet.
|
|
|
|
The Academy Bit · this is the ad
Filling in that sheet by hand, for every contract, is the job I built the toolkit to do.
The Tradies Academy toolkit is out of testing.
Set up a job and it reads your own contract, finds the clauses and the deadlines, and puts the dates in your phone calendar. When something goes wrong on site, it builds the notice from that same contract: Notice of Delay, Extension of Time claim, and the practical completion notices. The first notice on each job comes to me for a free check.
Variations aren’t in it yet. They’re next.
It’s going onto the first foundation members’ computers this week. There are a handful of foundation places: the toolkit and the whole Academy for $127 a week, locked in for as long as you stay. After that, the toolkit sits in its own tier at $197 a week.
It runs inside Claude on your own computer, so you’ll need your own paid Claude plan (Pro or above). I set it up with you.
Foundation places are hand-picked, so we’ll have a chat first. Not ready? Fair enough. Smoko’s still free every Tuesday.
|
|
|
That's the week.
Got a variation clause with a step that caught you out? Hit reply and send it through.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.