 | BY CONSTRUCTION CLAIMS & DISPUTES | | NEWS, INSIGHTS & THE STUFF THAT MATTERS | Issue 06 · Tuesday 20 October 2026
|
|
G’day.
Here's what's on this week:
|
Victoria’s retention claim, six months on
A big drop in commercial work approved
“We’ll pay once you…” Too late.
|
|
|
Straight in.
|
|
|
|
Doing the Rounds
VIC Security of Payment · Six months in
|
Before 15 April WAIT and chase it on the phone |
Since CLAIM and the builder has 10 business days to answer |
|
| IN VICTORIA, RETENTION IS NOW A CLAIM. |
|
|
| • | The changes to Victoria's payment Act started on 15 April 2026. Last Thursday made six months. |
| • | Retention money and bank guarantees are now a “performance security” under the Act, and you can serve a claim to get them released. |
| • | The claim has to identify the work, say what kind of security it is and how much, and state that it's made under the Act. |
| • | The builder has 10 business days (less if the contract says) to answer with a schedule. Send nothing, and it's liable to release the full amount on the due date. |
| • | If it still doesn't, there's a second-chance notice and then adjudication, the same shape as a payment claim. |
|
What it means for you
For a lot of Victorian subbies, retention is the money you quietly write off. The defects period ends, nobody rings, and you spend a year chasing it.
Now it has a claim and a clock, same as your progress claims.
The catch is timing. The second-chance notice has to go within 10 business days after the release date, and the builder's 10 days have to run out first. Serve the claim late and the quicker route can be gone before you start.
The good news: an early retention claim isn't thrown out in Victoria. It's treated as served on the first day the Act allows.
The move: the day your defects period starts, find the release date in your contract and put a reminder in a few weeks before it. If you can't work the date out from the contract, that's worth a proper look well before it comes around.
Victoria only. Queensland and NSW deal with retention differently.
|
|
|
|
The Number
44.8%
fall in the value of non-residential building approved across Australia in August
|
|
|
Commercial, industrial and community buildings. The value approved dropped to $5.53 billion in a single month.
July was the second-highest month ever recorded, so part of this is a big month coming off. One month is noise.
But approvals are where next year's work starts. If September comes in soft as well, expect more builders chasing fewer jobs. That pressure tends to land on the subcontract price, and on the terms that come with it.
ABS, Building Approvals, Australia, August 2026 (released 30 September 2026). Seasonally adjusted.
|
|
|
|
Off My Desk
You’re not the builder’s bank.
|
|
How it ran
| Claim day | Stage one claim goes in, saying it's made under the NSW Act. |
| Builder's deadline | No payment schedule. No payment. |
| Next business day | Second-chance notice. Five more business days to answer. |
| Five business days on | Still nothing. |
| Next morning | Notice of intention to suspend work. |
| Two hours later | “We would appreciate the following before payment is made…” |
|
| BY THEN, THE WINDOWS HAD SHUT. |
|
|
|
A plumber in Sydney finished the first stage of a residential job and put his claim in. Done properly, too. It said on its face that it was made under the NSW Act, which in NSW it has to.
Then nothing. No payment schedule (the builder's written answer saying what it will pay, and why). No money either.
So his office sent the second-chance notice the Act needs before adjudication. That gives the builder five more business days to answer. Nothing again. The next morning, notice went that he intended to suspend work. Two hours later the project manager replied:
|
|
…We would appreciate the following before payment is made: 1. A written schedule for completing the remaining rough in works… 2. The date of the pressure test… 3. Your list of outstanding items…
|
|
|
Fair things to ask for on a job. The wrong time to ask for them as the price of getting paid.
Here's how it works in NSW. If the builder doesn't send a payment schedule in time (10 business days at most, sooner if the contract says), it owes the whole claimed amount on the due date. A list of conditions turning up afterwards doesn't change that.
If it still doesn't pay, the Act gives the subbie options. Chase it as a debt, or go to adjudication (a fast, independent decision on the payment). And on top of either, give notice and stop work.
On the call I put it the way I'd put it to anyone. I'm not a bank. You're not a bank. You're not bankrolling their job.
In NSW, once at least two business days have passed since that notice, you can stop work until you're paid. While you're validly stopped, you're not liable for the builder's losses from you not being there.
One thing nearly tripped us. The claim was dated five days before it actually went to the builder. We'd worked every date off the invoice date, which would have had the second-chance notice going out too early to count. His office found it in the Xero history.
The matter is still running, so that's where I'll leave it.
What it teaches. A promise to pay with strings attached, sent after the builder's deadline, isn't a payment schedule. In NSW, once those windows shut, the Act sets the terms. And stopping work comes in an order: claim, deadline, notice, two business days. Skip a step and you're not protected.
Watch for. “We'll pay once you…” turning up after your claim's deadline has passed. Write down the day it arrived, and work out where the clocks are before you answer it.
General information only, and NSW only. Queensland and Victoria have their own versions with different steps. Stopping work is a big call and it turns on your contract and the facts, so get a proper look first.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Check when your last claim actually went.
Every date in that story ran from the day the claim reached the builder. The date printed on the invoice can be days earlier.
| 1. | Open your last claim in Xero and scroll down to History and notes. Most invoicing software keeps a similar log. |
| 2. | Find the line that says it was sent. Note the date and the time. |
| 3. | If it went after 5pm or on a weekend, count the builder's deadline from the next working day. That's the safe reading. |
| 4. | Write that date on your copy of the claim. |
And if the software has sent the same claim more than once, check before it goes again. A second send can look like a second claim.
|
|
|
|
|
The Toolbox
Notice of Delay and EOT templates, free
In that story, most of what was left to do was held up by things outside the plumber's control. That's when a notice of delay earns its keep.
Two Word templates, a Notice of Delay and an Extension of Time claim, each with a filled-in wet weather example.
|
|
|
|
Download the EOT claim See both wet weather examples
Free, Word format, no sign-up. Your contract sets the time limits and some are short, so read its notice clause before you rely on any template.
|
|
|
|
The Academy Bit · this is the ad
Every clock in this issue starts with a claim. If the claim doesn't hold up, nothing after it does.
The Invoice Checker. First two checks free.
Upload your claim, or pull it straight from Xero, and it runs it through the checks a payment claim has to pass in your state. Who it's addressed to, the wording your state needs, the description of the work, the amount. About a minute, and you get a report to keep.
It checks the paperwork. It can't make the builder pay.
After the first two, $9 a check or $29 a month. Not ready? Fair enough. Smoko's still free every Tuesday.
|
|
|
That'll do.
Had a builder put conditions on paying you after the deadline had passed? Hit reply and tell me what they asked for.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.