Canberra’s asking how subbies get paid. Closes Friday
What subbies get back when a builder goes under
The “defect notice” that started the clock
|
|
|
On with it.
|
|
|
|
Doing the Rounds
National · Have your say
|
The question Q10 How to get subbies and suppliers paid on time and in full |
Closes Friday 16 OCT 11:59pm AEDT 10:59pm in Queensland |
|
| ONE QUESTION. TEN MINUTES. |
|
|
| • | The federal Department of Employment and Workplace Relations is consulting on possible Commonwealth standards for the construction industry. |
| • | Question 10 asks what would best support full and timely payment for subcontractors and suppliers, without doubling up on the state and territory payment Acts. |
| • | Nothing's decided. The paper says there's no set scope or model yet, and asks what work any standards should even cover. |
| • | Submissions close 11:59pm AEDT on Friday 16 October. That's 10:59pm in Queensland. |
| • | It's an online survey, and small businesses are on the list of who they want to hear from. |
|
What it means for you
How often does anyone in Canberra ask a subbie how payment works on site? Not often.
Most of the people answering this will have a policy team. You've got something they haven't. You know what a 60-day term, a held retention or a “defect notice” that turns up after your invoice does to a payroll.
You don't need to write an essay. A few lines on what happened to you, and what would have stopped it, is the sort of thing a discussion paper can't make up.
The move: if you can spare ten minutes this week, answer Question 10. None of this changes your rights under your state’s payment Act today.
|
|
|
|
The Number
82.4%
of failed construction companies where the liquidator's first estimate for unsecured creditors was zero cents
|
|
|
That's 1,946 of the 2,361 first reports filed with ASIC on construction company failures in 2024-25. Queensland was 81%. Only 15 estimated better than 50 cents in the dollar.
Unsecured creditor is you. So the money you're owed is worth most the day it falls due, and a bit less every week it sits there.
A claim left in the drawer isn't patience. It's a bet the builder is still around when you get to it.
ASIC insolvency statistics, Series 3.2, 2024-25 (released December 2025). First-report estimates, not final payouts.
|
|
|
|
Off My Desk
It was called a defect notice.
|
|
How it ran
| Install day, lunchtime | Crew's completion photos. The roofers are in them, still working. |
| Install day, 5:40pm | Supervisor texts: roofers “just on site now about to leave”. |
| Four days later | The builder's damage photos are taken. |
| Three weeks after the invoice | “Defect notice” arrives. Payable now: $0. |
| Day 30 of 30 | Adjudication application lodged. |
| A week later | Invoice paid in full. |
|
| THE DEFECT NOTICE WAS THE PAYMENT SCHEDULE. |
|
|
|
A solar installer in south-east Queensland took the panels off a house so the builder's roofer could put new sheeting on. A couple of weeks later his crew came back and put a new system up.
Job done, invoice in. About thirteen grand.
Three weeks later the builder sent him a “Defective Works Order”. Dented roof sheets, it said, from his crew walking on them. About ten grand to fix, estimated. Payable now: nothing. And near the bottom, this:
|
|
…please consider this DWO as a formal Notice of Payment Schedule.
|
|
|
That line is the whole story. A payment schedule doesn't have to be called one. Under Queensland's BIF Act, a document that answers your claim, says what they'll pay and why it's less can be one. This one said so out loud.
Which meant the clock was running. In Queensland, once you get a payment schedule for less than you claimed, you've got 30 business days to apply for adjudication (a fast, independent decision on the payment). Miss it and that shot is gone.
The case didn't turn on law. It turned on what was already on his phone.
His crew's completion photos, taken around lunchtime, had the roofers in them, still working. At 5:40 that evening the builder's own supervisor texted that the roofers were “just on site now about to leave”. And the builder's damage photos were taken four days after the installer's crew had gone.
None of that proves who dented the roof. It does show who else was up there.
We put it together, sworn, with the photo data printed out, and lodged on day 30 of 30. Don't cut it that fine yourself. We used every day building the evidence.
A week later the builder paid the invoice in full, before it got to an adjudicator. They didn't say why. They paid “without admission” and kept the right to chase the roof sheets later. That's normal, and it's why he's keeping every photo.
What it teaches. A payment schedule can turn up in a hi-vis vest. A defect notice, an NCR, a backcharge notice. If it lands after your claim, puts a number on it and says nothing's payable, treat the clock as started.
Watch for. Anything from the builder after you've invoiced with a dollar figure and a reason on it. Write down the day you got it.
General information only, and Queensland only. Not every builder pays when the application goes in. How it plays out on your job turns on your contract and the facts.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Ten photos on the way out.
The installer's best evidence was photos he took without thinking twice. Make it a habit before you knock off.
Get:
| 1. | Your finished work, close up and wide. |
| 2. | Whoever is still working in your area, and what they're doing. |
| 3. | The way in and out. Scaffold stair, ladder, roof edge. |
| 4. | Then leave the originals on your phone. Some messaging apps strip the date and time out of a photo when you send it, so don't let the sent copy be the only one. |
Two minutes before you get in the ute.
|
|
|
|
|
The Toolbox
A payment claim template, free
Every story in this issue starts with a claim going in. Get that bit right and everything after it has something to stand on.
This template sets out what a claim needs to show: the work, what it's worth, and what you're asking to be paid. Fill in the blanks for your job.
There's a filled-in example and a how-to video if you want to see one done first.
One state note. In NSW, Victoria and most other states, the claim has to say it's made under that state's Act. Queensland and the NT are the exceptions. The template has a drop-down for that.
|
|
|
|
See a filled-in example Watch how to fill it in (23 min)
Free, Excel format. A starting point for your claim, not a substitute for reading the payment clause in your own contract.
|
|
|
|
The Academy Bit · this is the ad
If you're the one who opens the builder's emails, this week's story was about you.
Tradies Academy, $127 a week.
Payment claim and payment schedule templates, short videos on reading what the builder sends back, and a live group coaching call every week for the questions a template can't answer.
Templates are a starting point. A big or messy dispute still needs a proper look.
No credit card, no lock-in. Not ready? Fair enough. Smoko's still free every Tuesday.
|
|
|
That's the week.
Had a “defect notice”, an NCR or a backcharge turn up after you invoiced? Hit reply and tell me what they called it. I'm starting a collection.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.
This is the web copy of Smoko, the weekly email from Construction Claims and Disputes. Get it in your inbox. General information only, not legal advice. PO Box 918, Paddington QLD 4064
|