Queensland's adjudication numbers just landed
The 98 that never needed a decision
Twenty grand of meter, sitting in a shed
|
|
|
On with it.
|
|
|
|
Doing the Rounds
QLD Security of Payment
|
2024-25 324 applications $517m claimed |
2025-26 477 applications $1.94bn claimed |
|
|
|
|
| • | The QBCC published its 2025-26 annual report on 25 September. |
| • | 477 valid adjudication applications were lodged in Queensland last financial year. The year before it was 324. |
| • | Between them they claimed $1.94 billion, up from $517 million. |
| • | Just 38 claims over $1.24 million made up $1.88 billion of that. |
| • | At the other end, 106 applications were for $11,345.70 or less. |
|
What it means for you
Adjudication (a fast, independent decision on a payment dispute under Queensland's BIF Act) got a lot busier last year.
Most of the extra money is at the big end, and one year's numbers won't tell you why. But 106 applications under twelve grand tell you who else is using it. Subbies like you.
The figure I'd look at twice is on page 20. It's this week's Number.
The move: if you're owed money on a Queensland job, find out when your window to adjudicate closes. It's short, it's counted in business days, and it doesn't wait while you make up your mind.
|
|
|
|
The Number
98
Queensland adjudication applications withdrawn last year because payment was made
|
|
|
Between them, $320,577,123.
That's 98 times the money moved after the application went in, before an adjudicator had to decide anything.
Lodging is the step that tells a builder you know the process and you're prepared to use it. It doesn't guarantee a thing, and the report doesn't say whether every one of those was paid in full. But it's a lot of money that turned up once somebody stopped asking nicely.
QBCC Annual Report 2025-26, adjudication registry statistics.
|
|
|
|
Off My Desk
Not installed, so not paid.
|
|
|
A plumber on a commercial job in Brisbane paid the water authority over twenty grand for a meter, just before Christmas last year.
He had to. The authority wasn't issuing the water connection approval until the meter was bought. Not any meter, either. The one allocated to that job, by its meter number.
He couldn't pick the supplier. He couldn't pick the timing. And he couldn't use it on any other job.
So he paid it and put it on his next claim. The builder paid nothing against it, and gave this as the reason:
|
|
It's sitting in a shed and it hasn't been installed.
|
|
|
Behind that line is a clause most subcontracts carry. The builder isn't liable for unfixed plant and materials unless they're listed in the schedule. On this job the schedule item didn't list anything. It just set a security amount.
On its face, fair enough. That clause is written for stuff you choose to buy early, like a bulk pipe order to beat a price rise. No builder wants to pay for something that could walk off site.
A meter the authority makes you buy is a different animal. Nobody chose the timing. Nobody chose the supplier. And the approval it unlocked was one the builder needed to finish its own building.
So we didn't go after the clause. Builders are allowed to say they won't pay for loose materials. We argued the meter belongs in a different box altogether: authority charges. The builder's own contract documents put water meters in that box.
It's gone back in on his latest claim as an authority charge, with the authority's invoice attached. As I write this, it's not settled.
What it teaches. Money you pay to unlock an approval the job needs can get lumped in with materials you chose to buy early. Treat it that way and it sits on your account until the thing is fitted, and on a big job that can be the best part of a year.
Watch for. An unfixed materials item that reads Nil, NA or just a security amount, on any trade where the authority sells you the hardware. On every plumbing contract we review now, we write in a clause that makes authority fees and authority-required equipment claimable the month you pay them, installed or not.
General information only. How it plays out on your job turns on your contract and the facts.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Find the unfixed materials item in your subcontract.
The meter story turned on one line in a schedule. Here's how to find yours.
How:
| 1. | Open your current subcontract and go to the schedule or Part A at the front. |
| 2. | Search for “unfixed”. Some contracts say “off-site” instead. |
| 3. | Read what sits next to it. A list of items means those items can be claimed before they're fixed. “Nil”, “NA” or just a security figure means none can. |
| 4. | Got something big to buy before you can install it? Raise it with the builder in writing before you order. |
Two minutes. Better to find it now than on your next claim.
|
|
|
|
|
The Toolbox
When the builder says “you haven't given us X”
A plain-English fact sheet on Lean Field v E & I Global, a 2014 Queensland Supreme Court decision.
It deals with the builder who says you can't claim until you've handed over some piece of paperwork first. The court held that a hoop with no real purpose in getting you paid can't switch off your right to claim under the Act.
Different trap from the meter. Same family. Six pages, worked examples.
|
|
|
|
Free, and there is no form to fill in. Queensland only. A starting point, not a substitute for a proper look at your own contract.
|
|
|
|
The Academy Bit · this is the ad
The meter clause from Off My Desk wasn't in that subcontract. It goes into every plumbing contract we review now.
Contract Risk Review, $2,750 + GST.
Every clause and every schedule read, a departures schedule you can hand straight to the builder, a walkthrough call so you know what you are asking for and why, and one round of dealing with their response.
It's how the unfixed materials line, the authority charges and the rest get sorted before you've bought anything.
Reply to this email, or ring me and we will talk it through.
Not ready for a full review? Hit reply with the clause that is bothering you. |
|
|
That's the week.
Got something of yours sitting in a shed, waiting to be installed? Hit reply and tell me what it is. Bonus points for a photo.
See you next smoko.
- Jason
PS. Monday was a public holiday in Queensland and New South Wales, so it wasn't a business day under either state's payment Act. Counting days on a claim or schedule from last week? Add one.
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.
This is the web copy of Smoko, the weekly email from Construction Claims and Disputes. Get it in your inbox. General information only, not legal advice. PO Box 918, Paddington QLD 4064
|