The day your right to get paid actually starts
Why one bloke's claim was dead before he sent it
The smallest adjudication claim in Queensland last year
|
|
|
Straight in.
|
|
|
|
Doing the Rounds
Security of Payment
Victoria changed when you're allowed to claim. Queensland didn't.
|
Victoria Early claim survives |
QLD & NSW Early claim is dead |
|
|
ON OR AFTER. NEVER BEFORE. |
|
|
| • | On 15 April 2026 Victoria rewrote the part of its Security of Payment Act that says when you can put a claim in. |
| • | Reference dates are gone in Victoria. The earliest day you can claim is now the last day of the month you did the work in. |
| • | If you go early in Victoria, your claim survives. The Act treats it as served on that earliest day instead of throwing it out. |
| • | Queensland and New South Wales did not change. In both, a claim served before your reference date is invalid. Not late. Invalid. |
|
What it means for you
This one has been law since April and it barely got a mention outside the legal press.
If you work on both sides of a border you can't run one habit any more. The same envelope, posted the same day, gets a different answer depending on which state the job is in.
And Victoria being softer is not a free kick. Going early down there buys you nothing. Your claim sits parked until the earliest day anyway, and the builder's clock to answer you doesn't start until then either.
So the rule hasn't actually changed for anybody. On or after. Never before.
One more thing while you're looking at Victoria. Unless your contract says otherwise you get one claim per named month. Early is harmless. Often is not.
|
|
|
|
The Number
$234.09
the smallest adjudication claim lodged in Queensland last year
|
|
|
The biggest that year was $80,960,568.29. Both went through the same process.
In total there were 324 applications worth about $516 million.
Adjudication has a reputation for being something the big end of town does to each other. Somebody lodged for two hundred and thirty four dollars and nine cents.
If you've been sitting on a few grand because it didn't feel worth the trouble, there's your answer.
QBCC Annual Report 2024-25.
|
|
|
|
Off My Desk
His claim was dead before he sent it.
|
|
|
A plumbing contractor on a Queensland job. Good operator, organised office, claims out on time every month.
That was the problem.
He'd always put his claims in around the 25th. Get it done, get it off the desk, don't leave it to the last minute. Sensible in every other part of running a business.
Then we went looking at the contract. Schedule 1 set the date for submitting progress claims as the last day of each month, and another clause made that date the reference date. Which means his right to make a claim didn't exist on the 25th. It started five days later.
More than one claim had gone out that way. And the contract had a line in it that looked like a safety net:
|
|
A Progress Claim given before the Submission Date is deemed to have been
received on the Submission Date.
|
|
|
It isn't one. That wording has been tested and it doesn't work. A contract can't hand you a right the Act says you don't have yet.
By the time it came to me he was days off lodging. Two full adjudication applications were built. Submissions written, tabs A through to M, the lot. Both were abandoned.
We reset the claims against a date that actually existed and served them again.
What it teaches. Your right to claim starts on the date in your contract. Not before it. Send it early and in Queensland or New South Wales there is nothing there to claim against, so there is no valid claim.
The bit that catches good operators is that early feels like being on top of it. Nobody lies awake worrying about being three days early. It's late that feels dangerous.
One other thing worth saying. This job is the reason our Invoice Checker now works out your reference date for you and stops you before you send. It didn't do that until this landed on my desk. That is what the thing is for - so a trap like this gets caught by software at 4pm on a Thursday, instead of by me three weeks later with the application already written.
Details changed. The lesson isn't.
|
|
|
|
Two-Minute Fix
Go and check the date on your last claim.
Not the due date. The date you were allowed to send it.
How:
| 1. | Open your subcontract and find the clause that says when you can put a claim in. It's usually in the schedule or annexure at the front, not buried in the conditions. |
| 2. | Note the date. Last day of the month, 25th, whatever it says. |
| 3. | Now look at the date on your last payment claim. |
| 4. | If the claim went in before the date in the contract, you've got something to sort out. If you can't find the clause at all, that's worth knowing too. |
Two minutes. Do it before you knock off.
|
|
|
|
|
The Toolbox
The fact sheet on when you can claim
Plain English, eight pages, no legalese.
It walks through the High Court decision that settles when your right to make a payment claim actually starts, and what that means on a Monday morning with an invoice half typed.
What a reference date is. What happens if you go early. What happens if your contract doesn't name a date at all. Worked examples. And the Victorian exception from the top of this issue.
If you only read one page, make it the last one.
|
|
|
|
Free, and there is no form to fill in. A starting point, not a substitute for a proper look at your own contract.
|
|
|
|
The Academy Bit · this is the ad
Nearly everything that goes wrong on a job was decided before anyone turned up to site. The claim date. The notice periods. Who wears the delay.
Contract Risk Review, $2,750 + GST.
Every clause and every schedule read, a departures schedule you can hand straight to the builder, a walkthrough call so you know what you are asking for and why, and one round of dealing with their response.
The bloke above had his claim date buried in a schedule. A review is how you find that one before it costs you, not after.
Reply to this email, or ring me and we will talk it through.
Not ready for a full review? Hit reply with the clause that is bothering you. |
|
|
That's the week.
Go and look at the date on your last claim. If it went in early, hit reply and tell me what your contract says - I'll tell you whether it matters where you are.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.