Morning, and welcome to Smoko.
Quick word on what this is, then I'll get out of the way.
I've spent 38 years in construction. Most of what lands on my desk comes back to the same thing: subbies do the work, then have to fight to get paid for it. Usually not because they're in the wrong. Because nobody ever showed them the rules.
So that's what this is. Every Tuesday morning, one thing worth knowing about the industry and one thing you can actually do about it. Short enough to read on a break. No jargon, no lectures.
When I'm selling you something it'll be down the bottom, plainly marked, and you can skip it. One quick thing. Add me to your contacts so this lands in your inbox properly and the pictures show up. Takes a second and you only do it once.
Right. Here's what's on this week:
|
The collapse figures finally turned
Who actually pays inside 30 days
The paragraph that quietly deletes your quote
|
|
|
Let's get into it.
|
|
|
|
Doing the Rounds
Builder Insolvency
|
|
| • | ASIC recorded 3,472 construction companies entering external administration or having a controller appointed in 2025-26. |
| • | That is down from 3,596 the year before, a fall of about 3.4%. |
| • | It is the first annual fall since the current ASIC series began in 2021-22. |
| • | Construction was still 24.5% of all 14,153 company failures nationally, more than any other industry. |
| • | Figures released 24 August 2026. |
|
What it means for you
Everyone's read the headline by now. Insolvencies are easing, the worst is behind us, and so on.
Have a look at where the fall came from. In 2021-22 the construction figure was 1,284. It is now 3,472. So the number went down, off a base nearly three times higher than it was four years ago. That is an industry settling at a very bad level, and calling it a recovery is a stretch.
And a national average tells you nothing about the builder whose site you are on tomorrow. One in four company failures in this country is still a construction business.
So watch the things you can see on your own jobs instead. Payment schedules that used to come back in a week and now do not come back at all. Part payments with no explanation. Someone asking you to hold off claiming this month and catch up next month. Those are the tells that turn up well before an administrator does, and you get to see them before the market does.
|
|
|
|
The Number
57.4%
of small business invoices in construction paid within 30 days
|
|
|
That is the share of small business invoices in construction that got paid within 30 days by the large businesses that report their payment times. Across all industries the figure was 69.8%. Construction came second last of nineteen industries.
Here's the part that stings. Construction leans harder on small business than almost anyone, with 43.5% of what these big businesses spend going to small suppliers. Second highest of any industry. So the industry most dependent on subbies pays them slowest.
One more from the same table: at the 80th percentile, construction payment times hit 43 days. One invoice in five is sitting past six weeks.
It did improve by 3.2 points on the previous six months, so it is moving. Slowly.
Payment Times Reporting Regulator, Regulator's Update August 2026, covering 1 July to 31 December 2025.
|
|
|
|
Off My Desk
They kept his price. They deleted everything it was built on.
|
|
|
Closed out an electrical review a couple of weeks back. Apartment job in south-east Queensland, decent size package, supply and install.
The quote was a good one. Priced properly, with the qualifications a sparky needs on a job like that: a copper price basis, rock at cost plus a margin, and a list of exclusions for the things that are not his. Excavation, spoil, dewatering, asbestos, contaminated soil, scaffold and elevated work platforms, cutting and chasing, engineering certification, high voltage work, authority fees.
The builder accepted the price. Then sent through their subcontract.
Down the front of it, in the formal instrument, sitting under the list of contract documents where nobody reads, was this:
|
|
Notwithstanding any other clause of this Subcontract, if any annexure in this Subcontract includes any text supplied by the Subcontractor which is, or incorporates any part of the Subcontractor's standard terms and conditions, then that does not form part of the Subcontract.
|
|
|
Read it twice. It does not touch the price. The price is in the formal instrument and the price stays exactly where it is.
What it removes is every qualification the price was built on. The copper basis goes. The rock provision goes. All ten exclusions go. He is now on a fixed lump sum, with an open scope, for a job he priced on the assumption that none of that was his problem.
Why it bites.
On its face it looks like sensible drafting. Builders get sent quotes with the subbie's own standard terms buried in the fine print, and they do not want to accidentally sign up to someone else's payment terms. Fair enough.
But the clause is written wide enough to catch the whole quotation, and it starts with "notwithstanding any other clause". That means it beats anything else in the contract saying the quote is a contract document. So a subbie can point at the annexure list, see his quote sitting there, and still be wrong.
Nobody hides this one. It is right there in plain type. It gets missed because it is at the front of the document with the parties' names and the commencement date, and everybody skips that bit to get to the general conditions.
What it teaches.
Your money lives in the conditions attached to your quote, every bit as much as in the number at the bottom of it. If a contract can strip the conditions and keep the number, then the job you priced and the job you signed are two different jobs. Check what the contract does to your quote before you check what it does to anything else.
Watch for.
Any sentence starting "notwithstanding any other clause", anywhere in the front section of a subcontract. And any wording about the subcontractor's "standard terms and conditions" being of no effect. That phrase is the tell. It sounds narrow and it is not.
General information only, not advice on your situation. What a clause like this does on your job turns on your contract and your facts.
|
|
|
|
Two-Minute Fix
Go and find your quote in your last signed subcontract.
You are checking one thing: whether the document you priced the job on is actually part of the deal. If it is not named, it is not in.
How:
| 1. | Open the front of the subcontract, before the general conditions. Find the list of contract documents. |
| 2. | Look for your quotation, by number and by date. "The Subcontractor's quotation" on its own is not enough. |
| 3. | Read the paragraph directly under that list. That is where the clause undoing it usually sits. |
| 4. | If your quote is not named, or there is wording knocking out your standard terms, raise it before you sign. |
Ninety seconds, and it is the best ninety seconds you will spend on a contract all year.
|
|
|
|
|
The Toolbox
The Invoice Checker
Runs your invoice against the security of payment rules for your state before you send it.
You upload your invoice or photograph it, answer a few questions, and it tells you what is missing. Wrong entity name, no claim period, no reference to the contract, missing the words your state's Act requires. The small stuff that gives a builder a reason to knock it back.
Given how many invoices sit past 30 days in this industry, it is worth knowing yours is clean before it goes anywhere. Nine times out of ten when someone brings me a knocked-back claim, the problem is the invoice, not the builder.
|
|
|
|
Your first two checks are free, then $9 per check or $29 a month. It is a starting point, not a substitute for a proper look at a big or messy dispute.
|
|
|
|
The Academy Bit · this is the ad
 Nobody ever showed that sparky what to look for. That is the whole problem, and it is what the Academy is for. The Tradies Academy is the training and coaching side of what I do. Step-by-step video training, templates and tools you can use on Monday, real case studies, and a live group coaching call every week where you can put your own job in front of me. It all sits in one place, so you are not hunting through old emails for the thing you need. Big or messy disputes still need a proper look one on one. 14-day free trial, no credit card, cancel anytime. Then $127 a week. Or hit reply, or ring me on 0418 168 368. |
|
|
That's the week.
Go and check that quote is in your last contract. If it turns out it isn't, hit reply and tell me what the clause said. I will run the good ones in a future issue.
See you next smoko.
- Jason
|
Construction Claims and Disputes. 38 years on the tools and in the paperwork.
This is the web copy of Smoko, the weekly email from Construction Claims and Disputes. Get it in your inbox. General information only, not legal advice. PO Box 918, Paddington QLD 4064
|
|
Get the next one in your inbox.
Smoko lands every Tuesday morning. Free. Unsubscribe any time.
Join Smoko free
|